Project Details

Location: Fort St. John, BC

Time Frame: July 2015 - June 2016

Project Value: $60,000,000

Contract Type: Unit Rate

Services Rendered: Heavy Civil Construction

Project Summary

As Prime Contractor, Morgan facilitated the initial construction preparation work for the Site C Dam Project in Fort St John BC. The project included the excavation of 1.8 million m3 from the north bank and placed in a gully to facilitate the relocation of the creek. In preparation for the dam construction Morgan constructed 7.5 km of high-grade all-weather road, 2.4 km of this road was constructed within the Peace River along the toe of the adjacent escarpment. Roughly 750,000 m3 of alluvial gravel to facilitate the in-water road construction was excavated out of the center of the Peace River safely and without incident. In alignment with Morgan's core values of always finding a better way, Morgan provided value engineering by design building a pre-cast 3m diameter box culvert with 36m of bury as opposed to installing multi-plate corrugated steel pipe. Morgan is very proud to have been part of this high-profile project and construction team.

Project Scope

  • Built 5 km of conventional roads to access the construction site, including embankments and fills that were up to 34 m high

  • Constructed 2.5 km of roads within the river site access, as well as an abutment for a bridge

  • To construct the roads and produce aggregate, we excavated 750,000 m3 of material from the river's borrow sources

  • Designed and built a 2.4 m2 concrete box culvert and a temporary creek diversion system

  • Produced and placed various types of gravel, including sub-base, base, and filter layer gravels, to build the road

  • Riprap, which ranged from 10 kg to 500 kg, was produced and added to protect the slopes of the road

  • Culvert installation and drainage construction which included features such as ditches, cisterns, and stilling basins to manage water flow

  • Excavation and storage of potential acid-generating shales, including constructing a clay containment liner with HDPE cover

  • Stripping of organic material and subsoil to on-site stockpiles

  • Added topsoil and used hydro-seeding to establish vegetation on the back slopes of the road

  • Use of GPS survey layout and machine grade control to ensure precise construction of the project

Projects

Leading the way in 
heavy civil construction

Our proven track record of success in heavy civil construction is what separates Morgan from the rest of the industry. Take a look at some of our recent milestone projects.

Contact Us
Heavy Civil Construction

Calgary 24th Street Pond and Ogden Landfill Remediation

In preparation for the City of Calgary Green Line LRT expansion, Morgan was contracted to facilitate the reclamation and reconstruction of the old Ogden Landfill site. The project consisted of lowering the water table by installing a series of caisson sumps to draw down the water table then treating the water and removing all the total suspended solids, metals, and H2S gases. Upon successfully dewatering the site Morgan was then able to remove any remaining garbage and contaminated soils in advance of constructing the new 24th street pond, walking path, park and LRT track right of way.

Read More

Heavy Civil Construction

Crowsnest Pass Golf Club Access Road

Morgan was contracted to construct 2 kilometers of access road from Highway 3 to the new clubhouse, maintenance building, and driving range for the Crowsnest Pass Golf Club in Blairmore, AB. The project included excavation, blasting, gravel installation, paving, drainage features, and installation of utilities.  Highway 3 was widened and new traffic control features were installed to manage the increase in traffic to the facility. The project included several challenges, including careful monitoring of settlement and installation of geosynthetic layers to manage the risks of constructing road immediately above an existing mine shaft from an abandoned coal mine and adjacent to a sensitive wetland.

Read More

Heavy Civil Construction

Garden Plain Siteworks – Ph. 2 – Windfarm Development

Morgan was successfully awarded the Garden Plain Windfarm scope of work consisting of the construction of the access road network allowing the construction of 26 wind turbines. Morgan was able to assist the owner with providing project design models confirming design parameters and visibility. Through thoughtful planning and thorough execution, Morgan was able to facilitate the construction while minimizing disruption to the land owners farming operations.

Read More

Heavy Civil Construction

Highway 93 North Safety Improvements

Highway widening construction in several locations along Highway 93N to provide passing and climbing lanes.

Read More

Heavy Civil Construction

East Calgary Landfill – Cell Construction Phase 9

Construction of clay-lined landfill expansion and new access road.

Read More

Heavy Civil Construction

Site C Dam – North Bank Excavation

As Prime Contractor, Morgan facilitated the initial construction preparation work for the Site C Dam Project in Fort St John BC. The project included the excavation of 1.8 million m3 from the north bank and placed in a gully to facilitate the relocation of the creek. In preparation for the dam construction Morgan constructed 7.5 km of high-grade all-weather road, 2.4 km of this road was constructed within the Peace River along the toe of the adjacent escarpment. Roughly 750,000 m3 of alluvial gravel to facilitate the in-water road construction was excavated out of the center of the Peace River safely and without incident. In alignment with Morgan's core values of always finding a better way, Morgan provided value engineering by design building a pre-cast 2.4 m diameter box culvert with 36m of bury as opposed to installing multi-plate corrugated steel pipe. Morgan is very proud to have been part of this high-profile project and construction team.

Read More

Heavy Civil Construction

Highway 63 Widening

As part of the Province of Alberta’s campaign to widen Highway 63, Morgan was awarded the 0 - 14 km contract. Morgan was the prime contractor on this scope responsible for managing all traffic control, site safety, and subcontractor management. The project included 3.3 million m3 of earth and roughly 250 staff members to complete.

Read More