Project Details

Location: Riverfront Park, Fort McMurray, AB

Time Frame: July 2019 – November 2019

Project Value: $2,800,000

Contract Type: Lump Sum / Time & Materials

Services Rendered: Environmental & Demolition

Project Summary

Site remediation of a former industrial area of downtown Fort MacMurray, AB as well as construction of a new recreational walking path connecting the downtown core to the MacDonald Island recreational area. Morgan utilized our civil construction and environmental remediation skillsets to complete all scopes of work in house. A “turnkey” service to the city maximizing efficiency and minimizing cost.

Project Scope

  • Excavate 5400 m3 of soil that have been contaminated by PAH, transport and dispose of safely

  • Repair a trail that's almost 3 kilometers long

    • Remove bushes and trees, path realignment, install a base layer of gravel, and cover with pavement

    • Install new dirt and grass along the trail

  • Cover an area of 10,500 m2 with geotextile

  • Create a path made of asphalt, 3 meters wide, and 2.6 kilometers long

  • Build a retaining wall 35 meters long to keep the path from sliding downhill

  • Install seven culverts 5 meters long to help water flow under the path

  • Use 54 screw piles to install solar lights along the path

Projects

Leaders in environmental and demolition services

Our proven track record of success in environment and demolition is what separates Morgan from the rest of the market. Take a look at some of our recent milestone projects.

Environment & Demolition

Morinville Retail Fuel Outlet Decommissioning

The demolition, removal, and disposal of an existing retail fueling facility included the building, fuel canopy, three underground storage tanks, fueling dispensers, and all petroleum-related infrastructure. In addition to this work, the project includes excavation and removal of impacted soils.

Read More

Environment & Demolition

Surmont SAGD Pilot Plant Demolition

Abatement and demolition of plant included in our service offering was the processing and brokering of the recycled steel. Morgan provided a transparent sales and recycling program to the client in order to sell equipment as assets and to scrap and process the equipment that had no residual retail value. The result was a near “net Zero” cost to the client for the demolition activities.

Read More

Environment & Demolition

Firebag Camp Demolition

Morgan provided demolition activities on this site which included specialty equipment to crush and grind the demolition debris in order to maximize transport and take advantage of a reduced tipping fee at the disposal facility. Morgan also decommissioned all utilities both underground and above ground and worked directly with the property owner and their stringent health and safety standards.

Read More

Environment & Demolition

Watson Island “A-Mill” Demolition

Demolition of remaining structures at the former pulp mill site including two digester towers that were 280 feet tall and required significant engineering and pre-planning to topple and demolish. Morgan also managed waste caustic removal and chemical neutralization of residual waste as a cost effective alternative to packaging and offsite disposal.

Read More

Environment & Demolition

Seniors Lodge Facility Abatement and Demolition

Morgan Provided abatement and demolition of facility in the Peace River area. Abatement of the roofing materials was a challenge on this site. Morgan developed specific health and safety management planning for this task and developed an air monitoring program with the Occupational Hygienist to satisfy the Morgan safety standard and that of Alberta OH&S.

Read More

Environment & Demolition

Public Works Yard Remediation

Excavation transport and disposal of contaminated soils within city works yard. The challenge on this project was to allow the city maintenance fleet to continue to work within their yard as 90% of the yard was excavated to 4.5 meters below grade. Constant movement of the active work zone, safely managing active excavation, while allowing 40 different city works yard maintenance vehicles to come and go throughout the work day to access the various city facilities and buildings. Continual excavation and backfill of the site kept the work zone as small as possible while constantly shifting the access points for the city staff, keeping vehicles and ground personnel safely out of the work zone.

Read More

Environment & Demolition

Acheson Remedial Excavation

This project involved the remedial excavation and disposal of contaminated soil from a former tank farm/oil loading facility in a community area.

Read More

Environment & Demolition

Riverfront Park Remediation

Site remediation of a former industrial area of downtown Fort MacMurray, AB as well as construction of a new recreational walking path connecting the downtown core to the MacDonald Island recreational area. 

Read More

Environment & Demolition

Oak Bay Plaza Soil Remediation

Former retail gas station site that Morgan successfully remediated. The challenge on this site was to overmanage proximity agreements and underground utilities present in the adjacent property and boulevard. Morgan worked closely with utility owners and property owner, to ensure all existing facilities and utilities could be kept operational during the project.

Read More

Environment & Demolition

Medicine Hat Retail Fuel Outlet Decommissioning

The demolition, removal, and disposal of an existing retail fuelling facility include the building, fuel canopy, three underground storage tanks, fuelling dispensers, and all petroleum-related infrastructure. In addition to this work, the project included excavation and removal of impacted soils.

Read More